Torrent Power Substation Infra
High Voltage Switchyard, Step-Down Transformers & Synchronized SCADA Automation
The Torrent Power Substation Infrastructure project involved the engineering, procurement, civil construction, and commissioning of a mission-critical 132kV/33kV high-voltage electrical substation and automated switchyard designed to power expanding heavy manufacturing zones across Western India.
Client / Enterprise
Torrent Power
Power Utility & Energy Infrastructure Corporation
Project Location
Western India Industrial Grid, Gujarat
Industrial Corridor
Commissioning Year
2024
Completed
Delivery Model
Comprehensive Power Infrastructure EPCM
Single-Point Accountability
Torrent Power Substation Infra
The Torrent Power Substation Infrastructure project involved the engineering, procurement, civil construction, and commissioning of a mission-critical 132kV/33kV high-voltage electrical substation and automated switchyard designed to power expanding heavy manufacturing zones across Western India.
Valoris Turnkey Solutions orchestrated the complete lifecycle from switchyard earthmat design and high-voltage transformer foundations to Gas-Insulated Switchgear (GIS) installations, lightning protection grids, and centralized IEC-61850 compliant SCADA automation dashboards.
Operating in proximity to live grid infrastructure, our electrical engineering desk implemented zero-incident safety protocols, completed rigorous CEIG testing ahead of deadlines, and synchronized the substation seamlessly with the regional state electrical transmission corporation.
Engineering and commissioning a high-voltage 132kV transmission switchyard in a high-density industrial corridor with zero disruption to adjoining municipal power feeds and stringent grid code compliance.
Implemented modular Gas-Insulated Switchgear (GIS) technology to minimize physical footprint by 60%, deployed automated relay protection schemes, and pre-commissioned SCADA telemetry in parallel with civil construction.
Project CAPEX
₹210 Cr
Completed Power EPCM
Voltage Rating
132kV / 33kV
Transmission Grid
Transformer Capacity
2 x 50 MVA
Power Step-Down
Protocol
IEC 61850 SCADA
Remote Telemetry
Technical Scope Breakdown
On-Site Engineering & Execution Scope
Detailed breakdown of multi-disciplinary work packages executed under single-point Valoris management.
Switchyard Civil & Foundation Infrastructure
Heavy reinforced concrete plinths for 50 MVA transformers, fire barrier blast walls, oil soak pits with oil-water separators, and deep grounding grid.
Key Scope Items:
- Vibration-damped concrete transformer foundation pads
- Emergency transformer oil catchment & containment pits
- Switchyard perimeter security fencing and drainage network
Power Transformers & GIS Switchgear
Rigging, testing, and cabling of two 50 MVA 132kV/33kV power transformers, 132kV SF6 gas-insulated switchgear, and 33kV indoor vacuum circuit breakers.
Key Scope Items:
- Two 50 MVA 132kV step-down power transformers energized
- 132kV GIS bay with integrated disconnectors and surge arrestors
- 33kV indoor distribution switchboard with bus coupler
Substation Automation & SCADA Control
Centralized control room with redundant optical fiber telemetry, digital numerical protection relays, event recorders, and IEC-61850 protocol dashboards.
Key Scope Items:
- Full-redundancy SCADA control desk with remote trip commands
- Numerical distance, differential, and overcurrent relay panels
- 110V DC battery bank and uninterrupted station power supply
CEIG Inspections & Statutory Grid Energization
Complete statutory inspection coordination with the Chief Electrical Inspector to Government (CEIG), utility grid synchronization, and handover.
Key Scope Items:
- CEIG Statutory Inspection Report & Safety Sanction
- State Transmission Utility Grid Interconnection Clearance
- Comprehensive Relay Coordination & Trip Test Dossier
Lifecycle Roadmap
Milestone Execution Timeline
Structured progression from DPR feasibility and civil engineering to testing and commercial energization.
Load Studies, CEIG Sanction & Civil Plinths
Load flow studies, CEIG electrical drawings approval, earthmat grid installation, and heavy transformer plinth casting.
Transformer Rigging & GIS Erection
Precision rigging of 50 MVA transformers, gas-insulated switchgear assembly, SF6 gas charging, and busduct connections.
Control Cabling & SCADA Programming
Fiber optic routing, numerical relay wiring, SCADA software parameterization, and simulated fault trip testing.
CEIG Inspection, Grid Sync & Energization
Official CEIG inspection, high-voltage trial charging, live utility grid synchronization, and final handover.
Verification & Handover
Tangible Deliverables & Statutory Approvals
Comprehensive technical documentation, operational licenses, and verified compliance certificates.
Technical Deliverables
- Fully energized 132kV/33kV dual-transformer electrical substation
- Two 50 MVA step-down power transformers with automatic on-load tap changers
- Complete IEC-61850 compliant SCADA Control Room with remote telemetry
- Chief Electrical Inspector to Government (CEIG) statutory energization sanction
- State Electricity Transmission Corporation synchronization certificate
- As-Built electrical schematics, protection settings, and maintenance schedules
Statutory Clearances
- Chief Electrical Inspector to Government (CEIG) Statutory Sanction
- State Electricity Transmission Utility Interconnection Sanction
- Local Municipal Building & Electrical Safety NOC
- Pollution Control Clearance for Transformer Oil Containment
Strategic Commercial Impact
- ✓Powers over 45 industrial manufacturing plants with uninterrupted 99.99% grid reliability.
- ✓Reduces transmission line loss by an estimated 4.2% through low-loss GIS design.
- ✓Zero safety incidents across 320,000 safe man-hours during live grid operations.